CASE STUDY 05 RTO
SHIPBUILDING & MARINE ENGINEERING

Standard vessel schedule — major-resource optimisation delivered as an API

A leading Korean shipbuilder · master production schedule · 2025 – 2026 · delivered

Case screen: Standard vessel schedule — major-resource optimisation delivered as an API

CHALLENGE

  • The master vessel schedule allocated the building berth by splitting it into fixed zones and assigning work zone by zone, so the space at every zone boundary was stranded.
  • Constraints were reconciled manually from experience, so the same inputs could yield different plans depending on who produced them.
  • Adding a line raised planning effort roughly in proportion, which capped how often the schedule could realistically be revised.

SOLUTION

  • Rapid Task Optimizer supplied as the core optimisation engine behind the client’s own planning screens, delivered as an API and integrated with the client’s APS.
  • Berth placement modelled continuously — the actual position of each unit on the line rather than a discrete zone — over a five-to-six-year horizon in weekly buckets.
  • Insulation-shop placement for independent tanks modelled separately in daily buckets, with oversized tanks split across sub-tasks where shop capacity requires it.

RESULTS

  • Continuous placement recovers the space previously stranded at zone boundaries.
  • The same inputs produce the same plan, so the schedule no longer depends on which planner built it.
  • Adding lines or shops no longer increases planning effort; the same constraint set is applied automatically.