← All case studies
CASE STUDY 06 RTO
SHIPBUILDING & MARINE ENGINEERING

Offshore platform schedule optimisation

A leading Korean shipbuilder · offshore platform yard · 2025 · pilot

Case screen: Offshore platform schedule optimisation

CHALLENGE

  • Offshore platform construction schedules carry dense precedence, resource and spatial constraints, and slip expensively.
  • The baseline plan was built to be defensible rather than optimal, with float distributed by judgement.
  • Manpower and equipment utilisation were uneven across the programme, but the imbalance could not be quantified against an alternative.

SOLUTION

  • RTO applied to the client's baseline plan to generate an optimised schedule under the same constraint set.
  • Minimal-tardiness and minimal-makespan objectives evaluated separately, then jointly against resource-balancing objectives.
  • Critical path, bottleneck and causality analysis produced alongside the schedule, so the binding constraint is explicit.

RESULTS

  • Delay and tardiness reduced by transforming the baseline plan rather than replacing the client's planning process.
  • Resource utilisation balanced across manpower and equipment within the same delivery envelope.
  • Bottleneck and causality analysis identified where additional capacity would and would not change the outcome.

Your site could be the next case

Intro & Case Studiescontact@vivity.ai