CASE STUDY 04
DVI
SHIPBUILDING & MARINE ENGINEERING
Fabrication shop progress analysis from fixed CCTV
A leading Korean shipbuilder · fabrication shop · 2025
CHALLENGE
- Fabrication progress was reported manually and periodically, so schedule variance surfaced late and was frequently disputed between shop and planning.
- Drone capture is not viable inside a fabrication shop; the available sensing was existing fixed CCTV, at awkward angles and under difficult lighting.
- Block identity is hard to establish visually where many similar structures are worked simultaneously.
SOLUTION
- Continuous CCTV acquisition with real-time stitching and segmentation across multiple camera views.
- DVI block identification against the CAD database, assisted by OCR recognition of painted block identifiers where legible.
- Identified blocks and positions joined to the schedule database, producing actual progress against the original Gantt plan without manual entry.
RESULTS
- Progress reporting moved from a periodic manual survey to a continuous, hands-free measurement.
- Actual-versus-planned variance visible at block level, with the underlying evidence retained as imagery.
- Demonstrated that the DVI approach transfers from open-yard drone capture to constrained indoor fixed-camera environments.