← All case studies
CASE STUDY 02 RTO
SHIPBUILDING & MARINE ENGINEERING

Execution-plan optimisation across three yard processes

A leading global shipbuilder · LNG carriers, fixed platforms, naval vessels · 2023 proof of concept · 2025 – present

Case screen: Execution-plan optimisation across three yard processes

CHALLENGE

  • Pre-erection outfitting, pre-erection painting and erection block placement were planned separately by different teams, on inconsistent assumptions.
  • Painting alone ran across 40 temperature-controlled shops, with ten staff spending two to three days a week planning it.
  • Load was calculated by hand with no common basis, so plans were only partly optimised.

SOLUTION

  • A 2023 proof of concept on the yard’s own data established that Rapid Task Optimizer could optimise pre-painting placement automatically, absorb the real constraint set and support more than one objective.
  • The production system extends the same solver across three processes: pre-erection outfitting in two factories, pre-erection painting, and block placement across the PE yard’s two docks and NAT area.
  • The planner selects the objective — minimise tardiness, minimise schedule, or maximise output — with per-factory load levelling and a logistics-minimisation toggle.

RESULTS

  • Three processes that were planned separately now resolve against one constraint set and one objective.
  • Mean tardiness 25% lower than the client’s existing process on the same problem set, at proof of concept.
  • Weekly and daily optimisation with review and simulation, so a change can be tested before it is committed.

Your site could be the next case

Intro & Case Studiescontact@vivity.ai